How are gas-fired power stations supplied using DZK?

1 company with a published answer

  1. bayernets

    “bayernets expects the supplier of power plants to send a binding forecast in the form of a technical offtake notice (TON) in the NOMINT format. The TON must be sent to us by 22:00 CEST/CET on the day before delivery and again should there be any changes regarding the power plant offtake.”

Continue reading

Data formats and record details
Surface ID
urn:readyscan:corpus:buyer-question:bayernets-q17310477-answer-30fd7d9eb58e2379e749
Material fingerprint
fnv1a64:335367ec88e2aca8
Membership fingerprint
fnv1a64:1454b8ede2881180
Published
2026-10-29
Modified
2026-10-29
ready-scan-subjects/Q17310477
revision Q17310477:content:b8e56db65b4c29dc

Sources and dates

Feedback