How are gas-fired power stations supplied using DZK?
1 company with a published answer
bayernets
“bayernets expects the supplier of power plants to send a binding forecast in the form of a technical offtake notice (TON) in the NOMINT format. The TON must be sent to us by 22:00 CEST/CET on the day before delivery and again should there be any changes regarding the power plant offtake.”