How long does a full pre-audit take?

1 company with a published answer

  1. Cursorio

    “The typical timeline is about six weeks: one week of remote documentary review, two to three days on board for operational verification, two weeks to draft the report and corrective plan, then four to six weeks supporting the closure of non-conformities.”