How often should load bank testing be performed?

Answers from the sources

  1. OnPoint Generators

    “NFPA 110 requires annual load testing for emergency power systems. Many facility managers choose semi-annual or quarterly testing for additional assurance. For diesel generators that rarely run under significant load, we recommend at least annual load bank testing to prevent wet stacking and verify performance.”