How long does it take to build a custom home in Kelowna?

1 company with a published answer

  1. Palermo Homes

    “A typical Palermo custom home takes 14 to 20 months from your first design meeting to move-in. This breaks down roughly as: 3 to 5 months for architectural design and interior finishes, 2 to 3 months for permits and geotechnical assessment (longer on hillside lots), and 9 to 12 months of actual construction.”