How long does a data migration take?
1 company with a published answer
Transformativ
“It's set by data volume and quality, the number of source systems, and how many migration waves are needed. The final move usually happens over one cutover weekend; most of the effort comes before it, in mapping, cleansing and mock migrations. Profiling the data in the first weeks gives a timeline you can commit to.”